Murroes Church Hall
Client: Monifieth South Angus Church
Location: Murroes, Angus
Value: To Be Determined
Completion Date: To Be Determined
Design Team:
Quantity Surveyor: Morham and Brotchie
Structural Engineer: Narro Associates
Services Engineer: Max Fordham
CDM Services: Thomson Gray
The Murroes Church Hall is a C Listed traditional building from 1811, originally built as stables and coach house. It precedes the adjacent church by almost 40 years and was converted to support the church in the late 1990’s.
The congregation of Murroes is now part of the unified Monifieth South Angus Church, a consequence of the CoS, Presbytery Plan. The small church building is closed leaving the hall as the only facility in the rural locale that can support church and community life.
The brief is very simple, to upgrade and refurbish the halls to improve accessibility, flexibility and comfort for lots of activities; all factors that are current issues with the building. Lee Boyd and a design team were selected in 2024 to develop ideas tackling these issues.
The proposed design evolved in consultation from a limited number of options. The preferred proposal hinges on the need to increase the capacity of the hall and in doing so make it a uniform shape. To do this the new footprint takes space from the existing front facing external courtyard, requiring removal of 2 perpendicular outside walls. To increase flexibility, the new hall is subdivided into 2 smaller rooms, each with their own access.
It was not possible to satisfy the brief without also extending to the rear of the building with new toilets, storage and plant. The existing kitchen will be enlarged and refurbished and the small chapel lowered to achieve the same floor level throughout.
The design intent of the 2 extensions is to minimise impact on the existing character, but still sufficiently expressive to signify change.
The proposal received full Planning Permission and Listed Building Consent in July 2025.