Lady Haig Poppy Factory Refurbishment

Lady Haig Poppy Factory Refurbishment

Client : Lady Haig Poppy Factory
Location : Edinburgh
Value : undisclosed
Completion Date : Early 2022

Lee Boyd recently completed our work with Lady Haig Poppy Factory in Edinburgh, beginning in 2017. We supported the refurbishment and upgrade of their Poppy Factory and the associated offices for Poppy Scotland.
Prior to the main refurbishment works, an enabling works contract was commissioned to remove all the asbestos from the building. This was followed by the replacement of all 11 sections of the factory roof with new slate and new modular rooflights by the Contractors B&D Roofing. The original ‘Green Peggy’ slates to the Warriston Road buildings have been replaced with new Westmoreland slates, coursed and sized to match the original slates, with the remaining cement tiled roof being replaced with natural Cupa Heavy 3 slates. Sections of flat roofing and flashings have been replaced with high-performance waterproofing membranes.
Internally, Hatrick Bruce Contractors progressed with the full refurbishment of the building. Changes to the internal layout were made to physically link the Factory to the Poppy Scotland offices, aiming to improve working conditions and the visitor experience. The Poppy Scotland reception has been replaced and new toilets, lift and ramps all contribute to make the building more accessible for all.
Works were completed in early 2022.